2012 CSO Project - Public Notice

Posted Date: 3/19/2012

4/20/2012 Update:

The 2012 CSO Project is substantially complete.  The only items that remain are cleanup over the entire project area and a small amount of sidewalk and manhole work at the intersection of Pixley and Myrtle.

 

We ask that you water the areas restored on a regular basis as this is necessary for the new seeding to take hold.   To that end, the odd-even sprinkling ordinance will not be enforced in the project area for approximately one month (until May 20th).

 

Thank you for your patience throughout the construction and please feel free to contact Corey Kandow, Abonmarche Project Engineer (269-927-2295 ext. 112) or me with any concerns or questions.

 

3/16/12 Update:

 

B&Z Company took full advantage of the unseasonably warm weather this past week, making good progress on the water main at the Willa/Mount Curve & Lane intersection.  Water main and storm sewer work will continue in the coming week.  B&Z Company anticipates a water service interruption this coming Thursday (3/22/12)  in order to connect the new water main to the existing water main.  This work is expected to occur over the full work day - approximately 8 am until 5 pm - and impact property’s served by the mains on Lane Drive from Niles Avenue to the Willa/Mount Curve Intersection and the full length of Mount Curve.  Residents affected will receive a door hanger notice early next week with additional water shutoff information.

 

Please feel free to contact Corey Kandow, Abonmarche Project Engineer (269-927-2295 ext. 112) or me (contact information below) if you have question or concerns.

To view information pertaining to the upcoming 2012 Combined Sewer Overflow Project, please click here. To view the project map, please click here.